Trunk & Ceiling Renewal
The work during the dry docking of a vessel is listed below:
1.Trunking renewal, in detail:
*Procurement of required material 3/16’’ carbon steel
*Blasting and painting of the material
*Preparation of inserts for repairing the parts
*Cutting the damaged pieces
*Grinding with wire brushes to remove the rust
*Preparation in order to weld the new inserts
*Welding of the new inserts




2.Replacement of several sections of inlet trunk, that were corroded or had holes, in detail:
*Removal and disposal of the corroded sections
*Cutting the new pieces according to measurements
*Fitting the new pieces in the correct sections and welding them
*Cleaning the area
*Painting with one coating of primer


3.Removal of corroded Sound Eliminators
4.Partial renewal of the ceiling on Deck 4 Port Side
5.Doubler installation on floor of Deck 9 STBD & PS


Doublers on Deck 9